on 05-16-2008 11:56 AM
Dear All,
Iam Unbale to deliver the goods on current date,even the material is having sufficient stock ( un-restricted)
Order type is scheduling agreement
Waiting for ur valuable tips its urgent
\
Regards
Gowrish
c
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi gowri
Check wheather you have created any schedule lines in the scheduling agreements . If you have not created then delivery wont happen .
Secondly if you have created the schedule lines ,then check those delivery dates and also check wheather any pick , pack time days are maintained or not for the shipping point.
Regards
Srinath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Two things to check
1) Check if the schedule line is confirmed for the current date. If not then it would not help you deliver material in current date. Then you could try to do it in the future date when the schedule line is confirmed.
2) If stock is confirmed for current date and is availabe in unrestricted stock then too the schedule line is not confirmed then: Check if the Availability checkking rule is set for Sales order stock only. In ATP checking rule if the sales order stock is only to be considered then the system will not consider unrestricted stock. In this case a stock has to be posted against the sales order.
Regards
Nayan Shah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
When schedule line date is in future, while creating delivery in tcode: VL01N, select document creation date as schedule line date(future date) and then enter actual goods issue date as current date.
Regards
Uma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
The prerequisites to create a delivery...
1. atleast one schedule line should be due for delivery
2. there should not be a delivery block.
Check the scheduled delivery date in the scheduling agreement. It will automatically be updated in the delivery due list based on the delivery dates.
Thanks,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check whether there is a schedule for current date in the scheduling agreement. If there is no schedule line in the agreement and then if you are trying to deliver, it will not allow to you deliver.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.