In following customization PS-FICO integration is required.
1.Network Profile (OPUU) - Cost elements for Activities
2.Costing Sheet
3.Settlement Profile
- Allocation Structure
- Source Structure
- PA Structure
4.Commitment Items for Cashflow
Reward points of helpful.
Venkat Konda
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
PS Module is highyl integrated with CO module as project accounting details are defined in CO module. The details are as follows.
1. Costing :
Define of Cost Elements. Cost elements assignment to value category. Costing Variant etc.
2. Budgeting :
Exempt cost elements for budgeting
3. Result Analysis :
RA Version, Valuation method, Line ID for RA, assignment for RA, Define Posting Rules for Settlement to Accounting etc.
4. Project Settlement :
Define of settlement cost elements, Source structure, PA transfer structure etc.
5. Payments :
Commitment items
Hope the above will help you.
Regards,
Rakesh Pradhan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.