on 05-15-2008 3:57 PM
Hi All,
I want to schedule a job which should run daily in interval of 3 hours starting 12.30 PM and ending at 18.30 PM . I tried scheduling this job using the start condition in SM36 and made sure that the job is scheduled once in 3 hours .
But what the system does is that it divided the entire day into interval of 3 and executed the job 8 times .
Is there a way where I can restrict the system to execute only 3 times a day in the time interval of 12:30 to 18.30 PM.
cheers
Sridhar
Hi,
Try out keerthis suggestion and update us.
Thanks,
Sree.Manam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Easy way out:
Schedule 3 jobs that run daily:
First job runs every day at 12:30 pm.
Second job runs every day at 3:30 pm.
Third job runs every day at 6:30 pm.
Edited by: Keerthi Hiremath on May 15, 2008 11:56 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.