Hi All,

I want to schedule a job which should run daily in interval of 3 hours starting 12.30 PM and ending at 18.30 PM . I tried scheduling this job using the start condition in SM36 and made sure that the job is scheduled once in 3 hours .

But what the system does is that it divided the entire day into interval of 3 and executed the job 8 times .

Is there a way where I can restrict the system to execute only 3 times a day in the time interval of 12:30 to 18.30 PM.

cheers

Sridhar

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Try out keerthis suggestion and update us.

Thanks,

Sree.Manam

Former Member
0 Kudos

Easy way out:

Schedule 3 jobs that run daily:

First job runs every day at 12:30 pm.

Second job runs every day at 3:30 pm.

Third job runs every day at 6:30 pm.