Hi,

Goods issue has been posted for 100 no's of a material and customer called and advised to change it to 60 no's. We are trying to change the quantity but system is not allowing.

We don't want to cancel PGI.

How to rectify this?

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

After the goods issue has been posted, there is limited scope for changing the outbound delivery. In particular, no changes can be made to the quantities. At this point in processing, the delivery document has to reflect the actual physical delivery.

Only option would be to cancel goods issue for outbound delivery so that the goods issue posting is reset.

Answers (5)

Answers (5)

Former Member
0 Kudos

Hi

Dong

If you want to change delivery qty u need to reverse the PGI first by VL09 becose after PGI u can not change the qty. in vl02n. And after that only u can change the qty. to be deliver in the delivery in T Code VL02N.

Hope u will get help from this.

All the best.

Former Member
0 Kudos

Hi,

two options, one to reverse the goods issue VL09 and two create returns document and issue a credit memo nullifying the previous bill raised for 100 effectively making it 60 as required.

regards

sadhu kishore

Lakshmipathi
Active Contributor
0 Kudos

Dear Charlie

Not possible to change the quantity without reversing PGI via VL09.

thanks

G. Lakshmipathi

former_member184555
Active Contributor
0 Kudos

Hi

Posting the Goods Issue(PGI) means the Goods have left our premises and the company loses the ownership for that goods. As per my knowledge, you have to either cancel the goods issue (VL09) or Create a returns document and returns delivery and PGR for that 40 quantity.

Thanks,

Ravi

Former Member
0 Kudos

Hi Charlie,

Intresting scenario, already PGI has done so we dont have a chance to change the stock exept PGI reversal..

Regards

Sasikanth.Ch