cancel
Showing results for 
Search instead for 
Did you mean: 

schedule lines

Former Member
0 Kudos

Dear All

My issue is

when i create a oreder system giving schedule lines, means after 2 day delivery date even suffient sock is available

So,

I want to know from where that 2day picking by the system

even i have not maintaine any del lead tim in vov8

Thanks in advance

Regards

gowrish

Accepted Solutions (0)

Answers (7)

Answers (7)

Former Member
0 Kudos

c

Former Member
0 Kudos

There are 3 points ]

See in vov8 lead time if yes remove it

See in mm02 plan delivery time or lead time

See in shipping point picking packing time see all time in that and remove

Then create sales order.

ahmed

Former Member
0 Kudos

Dear Shankar,

Is this happening for all dates or particularly on weekends.

If this is happeneing for weekends then check your factory calendar settings.

In the plant defenition we give the factory calendar. If that factory calendar has only five days working, then delivery schedule lines will be created beyond those two days.

Regards,

Tajudeen S.

Former Member
0 Kudos

Dear Shankar,

Is this happening for all dates or particularly on weekends.

If this is happeneing for weekends then check your factory calendar settings.

In the plant defenition we give the factory calendar. If that factory calendar has only five days working, then delivery schedule lines will be created beyond those two days.

Regards,

Tajudeen S.

Former Member
0 Kudos

Hi shankar

in definatin of shipping point you can check you will get it.

in the sence shipping point you might have copied from the standard go overe there and open the shipping point what you have created. there picking packing loading time willbe there.

remove that and save come back and close all the windows and refresh 3 times and create sales order now and see.you will get it current date as delivery date.

Lakshmipathi
Active Contributor
0 Kudos

Dear Gowrish Shankar

Based on the settings made in OVLZ ---> In Pick/pack time wrkdys, no.of days whatever you maintain, your schedule line will be confirmed based on this.

For example, if 5 is given in this field, even if stock is available on the same day of order creation, system will allow to do PGI only after 5 days from the date of order created

thanks

G. Lakshmipathi

Former Member
0 Kudos

dear Lak

Thanks for valauble tips

i will go trough it

Regards

Gowrish

Former Member
0 Kudos

hi

may be you activated MRP level in material master.

rewards if helpful

mehar