on 05-15-2008 5:58 AM
Hi Gurus !
I was creating Purchase Requisition for a Project but by mistake took the WBS of another project in CJ20N ( Project Builder ) , and the PO has been made , even the GRN is also over . When Iam trying to open any S_ALR report it is showing 2 networks with different activities in one project.
I.R. ,Invoicing and GRN can't be reversed as booking period is already closed .
Please tell me how to correct it ? ?
Journal (Post an FI doucment) the costs from WBS to WBS.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Actually, the solution provided by all was good , but we still dont need to reverse any document or pass any JV for that. Without doing all these activities , we can correct the WBS which is wrongly assigned to PRQ.
I got the solution from Rohit Misra ( PS Consultant )
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi dhruv,
Please talk with Mr. Modi. because it is not in your hand.....
Regards
Lallan Yadav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dhruv!
Only Solution of this Problem is Pass The Journal Voucher. Becase every step is not in your hand ..and for that you have to take the permission from your RPO Head (Mr. Sreevastva and Mr. Nahar)..So dont think about whole process anly try to close current issue with Passing the JV.
Definetly this will not hit your JSR margin.
Rewards Point because this is the best Answer.
Regards
Dr. SMITH
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.