Activity dates

Former Member
0 Kudos

Hi,

I have problem while planning dates in activities. I have planned date in all activities and given relation between them. My problem is that in planning bord when i move the activity A's finish date then all interlinked activities should move with respect to activity A, but these are not moving. Logically it should move.

Is anybody have solution on it.

Thanks,

Sudhir

Accepted Solutions (0)

Answers (4)

Answers (4)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

I could find something Tcode: OPT7, select the profile and in diagram area tab plase check what is mentioned in constriant.. I suggest to make is blank i.e no constraint.

thanks..

Former Member
0 Kudos

Hi,

If the date, you keyed- in is the 'Actual Finish date', then it is standard system behaviour. Otherwise, pleae check whether the relationships maintained are Finish-to-Start.

Regards

Muraleedharan.R

Former Member
0 Kudos

Hi,

I am in planning stage, no actual dates. I used Finish to start relationship and contrains of activities are 'Must Start on and Must Finish on'.

Thanks,

Sudhir

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Becasue of the Constraints the activities will not move.

Try this:

Remove the constraint.

Enter the normal duration in the activities.

Maintain the relationships.

Later schedule as mentioned in my first reply.

Hope its useful.

Reward point if useful.

Thanks...

Former Member
0 Kudos

Hi,

But how the constrains should be removed. It is comming automaticaly. where the confugration setting to put the activity dates without constrains.

Thanks,

Sudhir

varshal_kachole3
Active Contributor
0 Kudos

hi,

on the intral activity, dates tab there on the dropdown list on the "must" you have the fourth option which is absolutely blank. please select for start and finish.

hope its useful.

Reward point if useful.Revert abck if any other issue.

thanks..

Former Member
0 Kudos

Hi,

I have tried it but not working, relation are coming by default. I think it require any confugration change butb where i don't know. Pls give solution on it i will award full points.

Thanks,

Sudhir

varshal_kachole3
Active Contributor
0 Kudos

Hi,

There on the dates tab you should have 3 options in the drop down list.: Must start on, can not start before, can not start later, and the fourth option is blank.

click on the must start on and there yu should be able to see these option

These options are not available?

If yes then select the bottom most option which is blank.

Check the authorization to change the dates.

Please revert back.

thanks..

Former Member
0 Kudos

Hi,

I know these four option. But when i select blank option till by default Must Start and Finsh is coming.

In SPRO, Transaction OPUC, I hided contrains field and then changed finish date of activity then also related activity date is not changing.

Thanks,

Sudhir

varshal_kachole3
Active Contributor
0 Kudos

Hi,

have you tried this option?

Tcode: OPT7, select the profile and in diagram area tab plase check what is mentioned in constriant.. I suggest to make is blank i.e no constraint.

thanks..

Former Member
0 Kudos

Hi,

Contrain feild is already blank. I think it is relationship problem. Relationship is not working. Where realtionship is maintained in configration?

Thanks,

Sudhir

Former Member
0 Kudos

Check settings of 'Adjust dates' in T Code OPU6.

Regards

Sreenivas

Former Member
0 Kudos

hi sudhir,

their is something called as float in PS which tells you the critical path in your project so you can make changes to those which fall under this critical path, plz refer the same ....

regards

pushpa

varshal_kachole3
Active Contributor
0 Kudos

Hi,

while opening the project planning board open with the project definition.

then select all. (This should select all the activities and WBS elements)

go to option and select the appropriate scheduling profile..

Now carry out the scheduling.

Hope its useful.

Reward points if useful.

Thanks..

Former Member
0 Kudos

Hi,

Select the activities and Schedule, then they will move.

Regards

Former Member
0 Kudos

Hi,

I have tried it and saved but it is not changing.

Thanks for immediate reply,

Sudhir

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Please check if any constraints are used in those activities.

Hope its useful.

Reward points if useful.

Thanks...