I would like to change the characteristics value of variant configured material. It is not allowing me to change the value in the Project builder The Project is assemble to order scenario
There is reference point and configurable material in CJ20n attached to network
While i create sales order based on the settings of standard network i get a pop up for entering the values of characteristics.
The material assigned in sales order is not configurable material.
After saving the sales order the project is created.
Where in the sales order can i change the characteristics value.
Regards
V Manoj
Hi,
The Sales material is not an configurable material. Also we have BOM transfer in PS and also the BOM material assigned in Project is configurable material
Regards
V Manoj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If I am correct, you have not attached a configurable material to Sales order. But In turn this is creating a Project like asembly order processing.
And in project you have used configurable material.
In this case you go to CJ20N. select the material and Extras --> Configuration --> Characteristics value assignment and here you should be able to change the characteristic.
Hope its useful.
Reward points if useful. Revert back if any other issue.
thanks..
Hi,
It gives an Message pop up "Item 001000 cannot be configured"
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In Tcode: VA02, go to extras-->configuration.
Here you can change the characteristics value.
Hope its useful..
Reward points if useful.
Thanks..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.