critical chain

adam_sobkowicz2
Active Participant
0 Kudos

hello

I would like to know is there any way to implement in PS a Critical Chain method of scheduling a project?

This method is a one of PMI recomendation so is it possible to scheduling a project with this scheduling methodology?

The main question is how to add time buffors to parts of the critical chain of the project?

Thank you

Edited by: Adam Sobkowicz on May 14, 2008 1:08 PM

Accepted Solutions (1)

Accepted Solutions (1)

varshal_kachole3
Active Contributor
0 Kudos

hi,

Please go to the network graphics in CJ20N,

Double click on the Relationship e.g FS. this will pop up a window where in Offset rel.ship you need to maintain the buffer time either + or negative (e.g +2 or 10-)

hope its useful..

Reward points if useful..

thanks

adam_sobkowicz2
Active Participant
0 Kudos

hi Varshal

Thank you for your suggestion. Yes, I think this is what I need, and it works fine.

Thank you very much.