I would like to know is there any way to implement in PS a Critical Chain method of scheduling a project?
This method is a one of PMI recomendation so is it possible to scheduling a project with this scheduling methodology?
The main question is how to add time buffors to parts of the critical chain of the project?
Thank you
Edited by: Adam Sobkowicz on May 14, 2008 1:08 PM
hi,
Please go to the network graphics in CJ20N,
Double click on the Relationship e.g FS. this will pop up a window where in Offset rel.ship you need to maintain the buffer time either + or negative (e.g +2 or 10-)
hope its useful..
Reward points if useful..
thanks