Hi..
We have Rep Mfg scenario , and we want to chk the material while in-process.
In the Mtl Mastr we have maintained Insptn type as 13 .
In Rate Routing we have maintained a operation with control key which requires Insptn characteristics n MIC is assigned in routing.
We have created a Planned order .
Now , requirement is dat system should not allow backflush activity until in-process inspetion rresult is recorded.
Whether Inspetion Lot gets created in Rep Mfg as soon as Planned Order is created..?
How to make the system to accomodate in - process inspection before backflush..?
Please guide me with soln
With Regards,
LN
Hi
Try by selecting reporting point in the rem profile.
suppose u have 10 operations ok
first 3 operations are production operation then 4th u want to go for inprocess inspection then for the 3rd operation select the control key as milestone key and 4th is quality control key with milestone confirmation.
Then when ever u go for backflush(MFBF) first u have to confirm the up to 3rd operation then 4th operation confirmation.
by this u can do the inprocess inspection scenario for REM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.