Rounding of qty from sale order to planned order

former_member311909
Participant
0 Kudos

Hi ,

There is sale order for 'X' material with qty 94,861meters, but when a planned order is generated the qty is rounding to 94,870 meters.

can any one give the reason, what are the things should be changed.

Regards,

somiraghu

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

Check the item category of the material being used..

go to SPRO>S&D>Sales>Sales Documents>Sales Doc Item-->Define Item categories..

check the section Transaction Flow for the indicator "Rounding Permitted". Uncheck if its checked.

let me know, if this doesn't work?

Reward points if useful.

Regards,

Raghu.

former_member311909
Participant
0 Kudos

Hi,

Raounding Value is not checked for item category

regards,

somiraghu

Answers (3)

Answers (3)

former_member311909
Participant
0 Kudos

Since, the rounding of decimals is for 2 places in CUNI.

Lakshmipathi
Active Contributor
0 Kudos

Dear somiraghu

Go to IMG path -- Logistics-General --> Quantity Optimizing and Allowed Logistics Units of Measure --> Maintain Rounding Profile. There check whether rounding profile is maintained for the said plant.

thanks

G. Lakshmipathi

former_member311909
Participant
0 Kudos

Hi,

there is no rounding profile maintained.

Former Member
0 Kudos

Hi, when the rounding of qty is checked it will take naeresst number , like 237 but take 240

former_member311909
Participant
0 Kudos

Hi,

Raounding Value is not checked for item category

regards,

somiraghu