on 05-14-2008 7:11 AM
hi ppl,
i have error while doing network costing.once i do cost calculation in cj20n only plan cost is calculating not actual cost.so where can i do actual cost and how it is reflecting.
regards,
shylini
Hi,
In case of internal activity if you maintain workcenter, activity type and work hours in the activity then after "confirmation", actual cost will be calculated.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
check the validity of the work center in CNR2 costing tab maintain a proper validity period.
Check the validity of the cost elements also and its assignment in KP26.
Have you maintained proper costing variant actual in Tcode: OPUV.
hope its useful.
Reward points if useful..Revert back if any other issue.
Hi,
Let us give a trial:
Step 1: Reverse the confirmation on that activity By Tcode: CN29.
Step2: Now go to Tcode CJ20n and Confirm the same activity again..here the system shoud give message while saving the project:
Do not save but say cancel and then go to extraslogscost calculation..
this is because if you ignore this message and still continues to save and went back to see the log the log gets cleared.
Let me know what the error is..
Thanks..
hi
check this out..
SPRO>PS>info system>cost revenue info system>project info database--set update control..
is the update checked, if not check it..
now check Tcode CJVC. are all the cost elements assigned in the value category properly..
then run Tcode: CJEN with test run on it.. first set delete and test run..then remove delete with onlytest run..
select object list
check whether ur getting the actual costs there..
if it does then remove test run and carryout the above cycle again..
run the report S_ALR_87013532.
do you see the actual costs there?