Hi,
i have some production tools which are very costly and i can use them for many projects ( I mean for many production
orders). I want to record them in system and i wish to track to which production order it is used and which is not used.
I heard that we can create the PRT as an equipment in plant maintenance and use them to record the usuage of it.
But please suggest me how to handle them like that in detail . the issue and usuage should also be recorded.
please explain me the process to use it in system.
regards
madan
Hi,
thanks for your answer.it is very useful. but i want to know how it is issued to the order. In which transaction.any movement type to be used and return from order any movement type to be used. please suggest in detail.
regards
madan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
thanks for your reply. my issue is how to issue the mateiral and return the material back to the stores in the system .
because always we issue to different projects and return them back after usuage.
please suggest
regards
madan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
these are three options which I can think of
1) If you are issuing to project order/production order then you can issue equipment PRT to order and receive back. You can track PRT issued to order and check/maintain capacity as well.
2) Create another Sloc for PRT issued and Issue to Sloc='Out' when you are issuing out to Project. When you receive back receive back from Sloc.
3) another options is to create functional location structure (IL01) if you have multiple lines / sites where PRT can be used. In this case you can move PRT around lines/site with functional location change for equipment.
Hope this helps-
HI,
Thanks for your reply. i am in need of recording the issue and return of the PRT after usuage. how it can be addressed in SAP.
It means PRT tool is in stores and it can be issued who ever requires and return it back to stores when he completes his job. how to monitor this.
please suggest
regards
madan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
Refer the following [link|http://help.sap.com/saphelp_46c/helpdata/en/fe/67f9609d6f11d189b60000e829fbbd/frameset.htm] and select Performance-based Completion Confirmations from Production
you can find the usage by checking the counter for the PRT equipment ,once the counter has reached the specified one in maintenance plan then you can have calibrate or check it again using maintenance order and put it to service
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
109 | |
15 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.