on 05-13-2008 1:38 PM
Hi,
Report SLR_87013535 (plan/ actual/commitments) shows commitments on a WBS .
I there are commitments balance showing in the report, even though final invoices have been posted for the PO's. The PO's are contract service PO's hence no GR's are getting created only invoice.
How can we close the commitments ?
Pls help
Hi,
for services please follow two steps:
1. Service entry:
The services actually performed (work actually done) by a service provider are recorded in a Service Entry Sheet with reference to the purchase order
2. Service acceptance:
Hope its useful..
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
U have to do Service entry for Service PO using Tcode:ML81N.
Then commitment is converted to actuals.
Thanks,
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.