Hello Cathy,
As far as my understanding
A delivery time agreed with the customer in the contract or quotation.
The delivery time in the contract is the time period that the customer
grants the vendor, from between the contract release order until the
delivery arrives.
In quotations, the delivery time helps you to agree on the latest
guaranteed delivery time once the order has been placed.
Dependencies
If you create an order with reference to a quotation or to a contract in
which delivery times have been agreed, the system copies that value to
the order item. You can enter delivery times at header or item level. If
the delivery time is at header level, it will influence the delivery
times for all items in the quotation or contract. However, you can also
enter a different delivery time for individual items at item level.
Use the settings in Customizing to decide which delivery times are
possible.
Similarly for quantity the things are maintained.
Please reward points if it helps you.
Sadanand.
Hello, Sadanand, my question is what impact if "fixed date & qty" this box is checked in scheduling aagreement. I have checked the forum, F1 & help SAP but no enough info is obtained. I just got a vague concept that it should be relevant to MRP.
Anyway, thx for yr prompt reply.
Any further feedback?
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.