on 05-12-2008 2:01 PM
dear gurus,
kindly tell how can i restrict confirmation of successor activity. Example in my Network structure diagram their is only one netwrok and three internal activities and relationship is finish start for all three activity.
1. activity ===>fs===> 2.activity ===>fs ===> 3.activity
As all can see the flow, i want is when i confirm activity 2 or 3 without confirming activty 1 the system should not confirm the successor activities.
kindly help its urgent
saqib usman
Done
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear all
I am still facing the problem in project system confirmation of activities. I have defined Finished start relationship (FS) among all activities in my network. However, system is allowing confirmation of any activity in the network irrespective of the relationship deifned.kindly tell me how can i restrict confirmation of successor activity without confirming the predecessor activity.
Example : In my Network structure diagram there is only one network with three internal activities and relationship is finish start for all three activity.
1. activity ===>fs===> 2.activity ===>fs ===> 3.activity
As all can see the flow, i want is when i confirm activity 2 or 3 without confirming activty 1 the system should not confirm the successor activities.
is their check box in confirmation paramenter to restrict successor activity confirmation.
in reply to above mail for customer enhancements: my abaper want to know about "actvitity relationship activty" table.
table were system store values for activity number with successor and predesoser activity
Edited by: SAQIB USMAN on May 12, 2008 7:30 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
we do not need milestones as our network containes more than 200 activitites. further the flow is very comlpex . is there any standard check box available to meet our requirements.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Saqib,
Please find below some userexits in confirmation:
CONFPS01: PS confirmation: Determine customer specific default values
CONFPS02: PS confirmation: Customer specific input checks 1
CONFPS03: PS confirmation: Customer specific check after op. selection
CONFPS04: PS confirmation: Customer specific input checks 2
CONFPS05: PS confirmation: Customer specific enhancements when saving
I have not tried any, check if they are of any help to you.
Regards
Hi,
Please use Tcode :SMOD
Use: Enhance ment as CONFPS02.
I never tried it still, the
help is pasted below for your quick referal.
Thanks.
Please reward if helpful.
-
CONFPS02 PS confirmation: Customer-specific input checks 1
The enhancement CONFPS02 contains the following components:
Function exit:
EXIT_SAPLCORF_007 PS confirmation: Customer-specific input check without changes
You can use this enhancement to subject the confirmation to your own checks, after the SAP standard checks have run. The confirmation can no longer be changed.
As well as the activity (AFVGD), the complete network header (CAUFVD) and the confirmation (AFRVD) are transfered in the interface.
Activities
1. Create the enhancement
Either create a new project or use an existing project.
2. Activate the project.
Your enhancement can only take effect after you have activated the project.
Further notes
Enhancements are, in contrast to modifications, release-insensitive, since they are not in the original SAP system, but in a name range that is reserved for customers.
You can find information about the general procedure for creating enhancements by choosing Utilities -> Documentation -> Onlinemanual
Hi,
you can try this:
1. Assign milestone to activity1 with milestone function as release following activities or the release upto stop ndicator with status change as Confirmed.
2. Assign another milestone to Activity 3 with a stop indicator (if you have chosen as Stop indicator)
Now in this case unless you release the activity 2 or 3 you can not confirm. And the release will only happen whn activity 1 is confirmed.
hope it helps. Reward points if found useful.
Thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.