Hi,
I f I define a Plant in R/3 and didnot define a node type in R/3 SPRO>DRP> Assign node types.
But when I Cifed the material to APO, it is transferred automatically as 1001.
1. How does the system know that it is a Location type 1001? or is it the default?
2. Are there any other settings that help the system decide the location type?
I noticed the R/3 SPRO> Enterprise Structure>Definition>Logistics - General>Define Location.
Thanks.
a plant is usually defaulted as 1001
unless you change the associated entry in the customizing table in the basic settings of DRP customizing
(customizing step Node Type Assignment --> Maintain Plant )
you can assign the following nodes here and they get mapped to the location types when they are CIFed into APO
A Store
B Distribution center
CD Customer warehouse
DC Distribution center
EW Central warehouse
PL Production plant
TS Stock transfer point
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.