on 05-11-2008 6:12 AM
Hi ffrinds,
can any any one help me re gardining this issue, i could appriciate you,
**
I should not be getting planned orders, should generate only PR's , which I can convert into PO, but no planned orders needed, when we creating project.
further the reference point is maintained on the activity
what are the setting and configurations , which are required , where i need to maintain to get only PR's while running MRP(MD02) iin material master data during project creation.
thanks
Madhu
&
Manoj
Edited by: madhu mandapati on May 11, 2008 7:13 AM
Hi,
i have done the testing with that settings ,but still i am getting planned orders.even i tested all scenarios
MRP4 tab Individual/coll. should be set to 1,2 and blank also.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In Tcode MM02 go to MRP2 tab in procurement type chose F if you want to create Purchase requisitions and Purchase orders.
If this is specifically maintained for the Projects then in MRP4 tab Individual/coll. should be set to 1.
hope is helps.
Reward points if found useful. and revert abck if any other issue.
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.