Resource not appearing while conversion from PPDS to SNP PPM

Former Member
0 Kudos

Hi,

While converting the PPDS PPM to SNP PPM i am not able to find the Resource in the SNP PPM even though it is available in PPDS PPM.

Thanks and Regards

Jignesh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Has the Resource been brought into APO as a 'Mixed' resource ? It needs to be Mixed to allow SNP as well to use as well as PPDS. Then In addition we have to define the Bucket Capacity in the PPM.

Ambrish Mathur

Answers (2)

Answers (2)

Former Member
0 Kudos

Jignesh,

Also check the consumption of the resource. While converting a PPDS PPM to SNP PPM system also checks th consumption. If the consumption is less than a day then the resource will not be considered.

Regards,

Abhi

Former Member
0 Kudos

Hi Jignesh,

Please check the Resource Master for that particular Resource. There is an indicator for "Not Relevant for SNP". If this indicator is set, during conversion the Resource is not taken into consideration in the SNP PPM.

Let me know if you have any questions.

Thanks and Regards,

Sharath Krishnan

Former Member
0 Kudos

Hi Sharath,

Thanks for the reply. Have check the indicator "Not Relevant for SNP" in resource master. It is not set in the current case.

Thanks and Regards,

Jignesh Gandhi