Friends,
I am trying to create a planned order on a resource at a plant. However it shows up an error message.
"
An application program called an LCA routine. The following error
occurred:
Time interval is not valid for dummy activities. Probable causes
error are an extremely long processing duration or times that li
outside the time interval (1.1.1970 + 30 sec, 1.1.2038 - 1 sec).
"
Could anyone help pme out with this,
Thanks in advance.
-A
Can you please check if the processing duration is compatible i.e. if this is generating very long lead time orders? May be you can try by changing the processing time or order lot size.