on 05-09-2008 9:29 AM
Deal friends here,
I've got a problem which I cannot really figure out or know why.
When we need to Realse or Confirm an activity,we usually use the t-code cj20n,here we can rel or cnf activities,networks and wbs from the low level to the top level.Like a WBS has a network,and the network has an activity;We can firstly REL or CNF the activity,then the network and finally the wbs.
But using CN22,when I try to rel or cnf a activity,the system informs me that the wbs has not been realesed yet.Does that mean if I want to make some status change on the low level,the top level should have already been set that status?
What should I do if I want to use CN22 just like cj20n?Or is there any other way which I can REL and CNF objects from the low level to the top level?Coz we should keep the usage the cj20n under control within a certain department.
thank you!
Hi,
For confirming the activity , the WBS must be released first.
After that, you can confirm the activity either in CJ20N or CN22.
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Acturally no!
With cj20n,we can rel or cnf activity while wbs has not been realsed or confirmed yet,and I think this is logical.When not all the activities and networks have been setted,wbs is PREL or PCNF,After all the activities and networks have been setted,the wbs is setted automatically to REL or CNF。
Edited by: Leo Zheng on May 9, 2008 10:53 AM
Hi,
The system behavior is correct. When you release & confirm activity in CJ20N, please note that the WBS status changes to PREL ie partially released that is why confirmation is allowed.
Whereas in CN22, WBS is not available for status change and hence you cant proceed with confirmation.
Hope this clears ur doubt.
Regards
Oh,I see...THX
But how could I solve the prolem?
We set different network types for different sections of the company in order to make the limits of authority of changing the projects' contents which they are not responsible of .But they should realse or confirm their own networks and activities.
Edited by: Leo Zheng on May 9, 2008 11:10 AM
Hi Leo,
1. Give authorisation of CJ20N to project manager/person responsible.
2. Create Networks in WBSE and lock all of them.
Edit->Status->Lock->All: Perform this in CJ20N for all networks.
3. Project manager will unlock first network to be executed and release the first activity in CJ20N. This will set WBSe status to partially released.
4.On release of first activity network can be handed over to CN22 team. This procedure shall be followed for rest of the networks.
Hope this helps
Hi,
You can assign different Status Profiles to different networks.You can keep same transaction control in these status profiles as you want to define that the network can be changed only by a specified employee group
To achieve this , you can create an authorization key and assign it to the relevant user statuses in that Status Profile.
Hope this helps.
Regards,
Amit
You can use T Code CJ20 as 'other way'
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.