05-09-2008 8:00 AM
Hi,
I have created a PO while doing GR i am getting the following error."Document 4500000187 does not contain any selectable items". If I try with other user id the GR process is hapenning fine. But it is blocked for my user id. I hope the following information will be helpful for this.
I have rated a work flow under which if any body creates PO i am authorised to release the PO. the workflow is working fine I am able to release the PO of others. But if i create I am unable to do the GR process
Please help me out.
Regards
GK
05-09-2008 4:33 PM
Hello,
Please check up the release status of the PO using ME23N. Normally, the creator cannot release PO due to compliance requirements.
Thanks,
Venu
05-09-2008 9:01 PM
To do the GR the PO needs to be released- so the first check is PO should be released
Secondly check the Received qty if it is already received also check the tolerance level set up on the PO
Based on your findings please check and we can advise.
10-22-2013 6:50 AM
Hi All
We have an issue here. Kindly give your valuable
suggestions.
There is an account assigned PO (F) with 16 items out which all
15 items are GR’d but line item 16 is pending to be GR’d. Please note that all the items are text
materials. Whereas invoice is done for all the 16 items. Now when I go to GR the 16th item the system issues error “No Selectable Items for this PO”. Could you please let me know what could be the reason because in ME2N the system shows line 16 is still to be delivered and in MIGO it is showing the above mentioned error message.