How can we customize OPSG

Former Member
0 Kudos

Good Morning Experts!

What is the basic use of this transection ......OPSG..

How can we implement this in our froject(Customer Project)..PLease guide Us

Thanks in Advance

Regards

Smith

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Change Profile is the profile that control change management in network. We are assigning change profile to network type in OPUV. Change profile will be created in OPSG & various structure of the network such as activity / activity elements / materials etc will be definesd. In the change profile we are defining the message to be generated during change of network structure such as activity release, operation released. We can make mesage to be generated as warning / error / information etc based on business requirments.

Hope this will help you.