on 05-09-2008 5:25 AM
Hi
I have create two activities(one internal and other External) under one WBS Element.
I have complete the process of confirmation(for Internal activity) and Purchase process for external activity.
Now i can see both the planned and actual costs of those activities.
Now i want the see the costs at WBS Level, which is now happening.
pl guide me, where i can see and what will be the process.
Thanks & regards
pavan
Hi Pawan !
You can see all the Reports in project system under-
Logistic->Project System->Information System->Financial->Varius reports are given there
you can use Report-
S_ALR_87013533 - Plan/Actual/Commitment/Rem.Plan/Assigned
Thanks
Rewards Point if helpful
Regards
Smith
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In OPSV, check whether both check boxes are ticked for network ie order type 20.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hI,
Plz use transaction S_ALR_87013532.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can check using S_ALR_8701353 report.
Reward points if helpful.
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.