Hi

I have create two activities(one internal and other External) under one WBS Element.

I have complete the process of confirmation(for Internal activity) and Purchase process for external activity.

Now i can see both the planned and actual costs of those activities.

Now i want the see the costs at WBS Level, which is now happening.

pl guide me, where i can see and what will be the process.

Thanks & regards

pavan

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi Pawan !

You can see all the Reports in project system under-

Logistic->Project System->Information System->Financial->Varius reports are given there

you can use Report-

S_ALR_87013533 - Plan/Actual/Commitment/Rem.Plan/Assigned

Thanks

Rewards Point if helpful

Regards

Smith

Former Member
0 Kudos

Hi,

In OPSV, check whether both check boxes are ticked for network ie order type 20.

Regards

Former Member
0 Kudos

Hi

Checking is there for both the boxes

Thanks

pavan

Former Member
0 Kudos

hI,

Plz use transaction S_ALR_87013532.

Thanks

Former Member
0 Kudos

You can check using S_ALR_8701353 report.

Reward points if helpful.

Venkat

Former Member
0 Kudos

Srinivas

pl check the T-code

Thanks