Dear Guru,

What is commitment date in Sales Doc Type OR (Setting - General Control).

Thansk in advance.

Dhananjay

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

hi dhananjay,

Commitment date is the date we have promised/commited to the customer that the goods or materials will be delivered on or before that date

thanks,

krishna prasad

Lakshmipathi
Active Contributor
0 Kudos

Dear Dhananjay

The commitment date is calculated using the delivery time for releases to contracts with delivery times, or sales orders that refer to quotations containing delivery times. The committed quantity results from the agreed delivery time or the confirmed quantity, according to the calculation rule set here.

You can set the following calculation rules:

o A: Consider agreed delivery time

Here, all required schedule lines are committed for the date that lies at the agreed distance from the delivery time, according to the date on which the order was placed. If the customer requests a later date, this can be confirmed. The confirmation does not affect the calculation. If you do not enter a delivery time, the system does not calculate a committed quantity.

o B: First confirmation date

The committed quantity is calculated according to the first

confirmed quantities. If a delivery time exists for the item, the

system takes it into account, as in calculation rule A, and confirms the earlier date. The commitment date is recalculated if the material, quantity, first date, or delivery time change. The quantities confirmed then are valid once the document has been saved.

o C: First confirmation date

Rule C is the same as calculation rule B but for new items. If you save a document again but the system can confirm more for the customer, the more favorable situation will be saved as the commitment. As in rule B, the commitment date will be recalculated if changes are made to the material, quantity, requested delivery date, or delivery time.

o No entry

Commitment dates are not calculated or displayed