on 05-08-2008 1:00 PM
Dear SAP EXPERTS
What is the general Document flow for value contract :WK1
When I am creating value order with respect to Value Contract.
the error appears that the document coping not possible.
regards,
Amlan Sarkar
Hi
This can be controlled in the configuration of the Item category used for your value contract. In the field Completion Rule - you have to select the value that the referencing can be made until the Target Value is achieved. Then you will not be allowed to create release orders for values more than the contract.
Thanks,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Amlan Sarkar,
Please refer to the following link of Value Contract:
http://help.sap.com/saphelp_47x200/helpdata/en/dd/55fd7a545a11d1a7020000e829fd11/frameset.htm
Hope it could help.
Regards,
Smile
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Freinds,
Thanks for your reply.
If I create a value contract for Rs 2000.
Now The Order Created againsts of Reference to the contract it should not exceed Rs 2000/-
I can create the order value more than the contract value ..
I see the released value is more than the the contract value.
How Can I restrict the order value to the Contract value.
regards,
Amlan
Hi
In VTAA make copy controls between WK1 and OR and also at item level.
Thanks,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.