Regarding flexible data screen

Former Member
0 Kudos

Hello all,

I want to add one additional tab in activity detailed screen. In project structure i have selected the required network and hen gone to setting - Layout detailed screen - chose the required detail screen and save. But the problem is that i am getting only one tab which i mentioned and the other tabs disappear.

what can be done additionaly to get the additional TAB apart from the original tabs in activity.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Sudheer,

The following SAP enhancement is available for networks in the Project System:

CNEX0008: Customer-specific fields in network activities

You can use this enhancement to add new customer-specific fields to network activities in table AFVU. To process these fields you can create your own screen, which the user can call up when maintaining networks. or from the project planning board.

Hope this helps.

Regards,

Amit

Former Member
0 Kudos

Hi,

You will have to go for development. Use enhancement CNEX0008. Goto Cmod and check documentation for this.

Regards

Edited by: Shrikant Rakate on May 8, 2008 5:02 PM