Hi,
When I create a sales order lets say for material "A".
And I want to deliver this component from sales order. With Production order.
I have attached the material "A" in Project to an activity with a positive quantity, in MD04 I am unable to see the planned order for that.
Project is released and it has created a order reservation but i am unable to convert it into the Planned order how it can be achieved.
Material is not relevent for the MRP.
Please suggest some solution.
Hi
Go in md51 t code.Tick mark with hierarchy and select 3 in first three as 3 in mrp control parameters. now u can see plnd order ,pr and all the details related with that project
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please run project MRP (MD51), selecting option 3 (planned orders) against create P.req. field under MRP control parameters tab.
Planned orders will be created automatically & u can see in MD04 also.
Thanks
Kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Plz use transaction MD11 to create Planned order.
Reward points if useful.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.