Hi,

I would like to confirm the TO and I have the process 2 steps confirmation.

I would like to know what is been changed in the table LTAP after the first confirmation because the light turns to yellow.

for exemple after the second we have in the field "LTAP-PQUIT" = X and the light turns to green.

Thanks

dede

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Check for the field LTAP-PVQUI,it becomes 'X'.

Thanks

Seshu

Edited by: Seshu Maramreddy on May 7, 2008 2:01 PM

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello Dede,

Can you please explian about 2 step picking process ,i am not aware of configuration,if you provide configuration steps and process details that would be great.

Thank you

Thanks

Seshu

Former Member
0 Kudos

Hello,

I have configurated the GR with 2 steps confirmations. you have to confirm when you take the Material from point A and when you put the material in point B.

In Customizing you just have to difine the search sequenz in Strategies von Logistic execution.

ciao