on 05-07-2008 3:46 PM
Hi,
Couple of years ago, during carve out, one of the contracts was deleted.
A PO created against that contract carries some open quantities. Now our purchasing wants to close this PO, either by changing the quantity to delivered quantity (delivered quantity is lesser than PO quantity), or by checking the delivery complete box. But they are not able to do so, as there was no contract number exists in the system table.
I propose to create a contract with the same number mentioned in the PO and then to change the quantity in the purchase req and PO. However now the system issues a dump error message "ME 808: System error: error during update Table EKAB".
Can anyone help how to resolve the issue?
Any body had similar situation?
Thanks for your help.
Regards,
Shiva
How did you "carve out" and delete the contract?
Standard SAP transactions would not allow to delete the contract, if you have still open documents, or if the contract is not closed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.