i have some questions for the Capacity check problems in Project System.
1. if one Person is assigned to diffierent Work Centers, for example, person A is assigned to Work Center 01 under Plant 01, and Work Center 02 under Plant 02, how can i do the Capacity check?
if i want to use A of Work Center 01 in the Project, the System will only check the Capacity of 01, or both of 01 and 02?
2. What is the Pooled Capacity?
Rgds,
Liang
hi,
1.Capacity check takes place at plant level itself..
2.Pooled capacity:- This is created separately in [u wil find in PP] and this capacity can be used by different work centers.
regards
pushpa