on 05-07-2008 9:06 AM
Hi,
can anybody know if project's already finished(closed)?
how to change status to finished/closed?
Thanks
Long
hi,
to close a project follow the steps in the sequetial manner:
1. CRTD (Planning Phase)
2. REL (Excecution Phase)
3. TECO (Technically close) after this status only final settlement can be done.
After final settlement go to step 4
4. CLSD (Project Closed)
Thanks!
Reward points if found useful.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
1. Go to Tcode: CN42N,
run this report for all the Projects in question or a range of project.
2. After excecuting the report select layout and change layout and from the layout section on the left select "Status"
And execute this report.
3. Now you know the status of all the project. This is a complete list of the all the Project you have selected.
Hope it answers your question.
Reward points if found helpful
thanks!
Hi,
IN CN41 report you can check the status of the project.
Please reward points if useful
Regards,
Laxminarsimha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.