Revised Project Start & Finish Dates

stheurkar
Active Contributor
0 Kudos

Dear All,

Where i can see Project orignal start & finish dates and Revised start & finish dates

Is their any report or transaction available.

Pls confirm me.

Thanks in Advance.

Regards,

Sandeep N.Theurkar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

If you are using project version functionality then this can be available. You can compare base line projects with various stages of projects & dates can be compared in CN41 / CNS41.

Regards,

Rakesh

Answers (1)

Answers (1)

former_member201206
Active Contributor
0 Kudos

Hi Sandeep,

The project system does not keep the original dates somehwere automatically. If you would like to have such 'baseline', a option is using version as mentioned above. An alternative is just transfer the basic dates to the forecast dates as base line, after the planning is finish. In this way, you get two sets dates of the same object.

Kind regards,

Zhenbo