Can materail be consumed for a project from project stock of some other project.
I mean if I have project stock of one project, can I directly consume it without transfer for some other project.
Hi,
U can consume materials for a project from Plant stock. But one project stock can't be consumed directly against another project. Need to transfer first & then only can be consumed
Thanks
Kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
No it is ot possible, because when a material is attached for a project which is project specific material it creates a reservation and that material can be only be consumed for that partucular project..
For the use of the some other project, then you need to transfer the material from project to project with movement type: 415Q in Tocde: MB1B
Reward points if found useful.
Thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Not poosible. U have to transfer the stock to the project to which u would like issue.
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.