Scrapping a Removed/Replaced meter

Former Member
0 Kudos

Kindly refer to the implementation scenario below:

A meter(serial number) is issued from stock against a work order(Mov type 261) ,which get physically installed at a site.The issue is done through the transaction MIGO.

Now after a meter removal/replacement the old meter needs to go back into a "scrap" storage location,as these will be never re-used again.

Would appreciate,if you can put forth your ideas on how to do this,in terms of movement type to be used,whether it can be done from the same transaction(viz Transaction for removal/replacement).

Thanks in advance

1 REPLY 1

Former Member
0 Kudos

Create a New Movment type to receive the old meter into the stores with Xn MB1C in storage location scrap.

As Meter is in ESTO status , the meter canot be used for installtion/replacement.

Create new user status SCRP for Scrap, Change user ststus of the meter to SCRP.

Put a user exit in Xn MIGO to block issue of meter having user ststus 'SCRP'.

For doing this with Replacement/Removal Xn, use a User exit & run BDC for above steps in the background.

hope this helps..

regards,

Mahesh