Hi Experts,
In CJ20N we created External Activity, after which PR is automaticall generated,after that PO is partially created.
Now the scenario is...
When i come to External Activity & change the Activity Qty it allows me to do so.
Example.
PR : created for 100 hrs
PR released
Then PO created for 30 hrs and released the same
Then we changed and reduced the hrs of the same PR from 100 to 20
It allows doing and never gives an error since a PO has been already released for 30 hrs
Can someone through light on this how to stop person from not changing the Activity qty once it is saved.
Points will be Awarded..
Regards
Raj
Hi Raj,
I think, a validation rule should be the right one to make such additional check.
See 'Maintain Validations' under Operative Structures -> Network.
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.