on 05-06-2008 11:24 AM
Hi,
In the calibartion order how is teh inspection lots get generated?
hi
there are 2 ways
if you have assigned the inspection type to the maintenance order then as soon as you release the order system will create an inspection lot
if you assign the inspection point to the task list and assign to the maintenance plan ,then while scheduling system will generate the call object as well as inspection lot
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
yes you have to assign the inspection type 14 to the order type in IMG activity
other process
Create a task list with inspection point 300 and assign the suitable inspection characteristic
Assign this task list to the maintenance plan
Schedule the maintenance plan
if your current value has reached the planned value then system will create an maintenance order which in turn create the inspection lot
regards
thyagarajan