on 05-06-2008 8:07 AM
hi,
when i try to export a client in production after 2 minutes the scheduled process was cancelled, in SM21 it shows TSV_TNEW_OCCURS_NO_ROLL_MEMORY , and in ST02 under the Buffer column for Export / Import , the Swaps numbers are in red.
lately my production server has been upgraded to around 100G of memory, i think the parameter is not configured properly yet to take advantage of the available resource.
pls advice which parameter to configure or look into whenever there is increase of memory.
thanks.
comment and advice will be appreciated.
regards,
kent
Hi kent,
SAP note 133909 should help solve your issue.
Regards
Juan