Production blocking

Former Member
0 Kudos

Hi,

Is there a way in SAP to proceed the order into planned order or into production even it has a credit block? Is this possible?

Thanks.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member183879
Active Contributor
0 Kudos

I think it is very much possible. In SD, there is no functionality to block the creation of planning order based on credit check. It only controls teh creation of delivery and invoice based on credit check status and nothing else.

So if you just enable the creation of planning order for sales order, it will automatically happen irrespective of the credit check status.

If i am not correct, please let me know.

Former Member
0 Kudos

But when im transacting an SO with a credit block, it does not create a planned order... is there any set-up or config that the system is beahving this way?

Thanks.