Operative Indicator Problem

Former Member
0 Kudos

Good Maorning Experts,

I have a problem of planning indicator.actully i want to plan the cost in those WBS element for which Planning indicator is set in project definition .

as per me-

1 if we set planning indicator in OPSB , we can plan the cost for those WBS element for which planning indicator have been set in project definition .

2.if we not set that in OPSB we can plan the cost in all the wbs elemenet with or without set in project definition

but here when i am follwing this concept error is coming at the time of seting in project definition

please clear me from where I can resolve this

thanks in advance

"Rama"

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hai Rama,

Can u xplain the error message ?? You are right that if donn set planning element indicator in OPSB, you shud b able to do cost planning to any WBSE in CJ40.

Thanks

Saikishore Ganga.

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Please follow these steps:

1 . Create the cost element groups in T. code: KAH1 (FICO can help you with that) e.g. Cost and Revenue.

2. Create a planning profile in T.code: OPSB and assigne these groups in the detailed plannng area

I believe you have checked the plannning element in OPSB as well.

Mention the time frame e.g Past as 3 years and Future 5 years.

Check mark the total values and annual values as well.

Mention the cost element for the revenue element for billing plan as well.

3. Maintain this Planning profile in OPSA in controlling tab.

4. Set the planning opertive indicator to the WBS Elements.

Hope it helps.

Revert back if any other issue is cropping up.

Reward points if found useful.

thanks!

Former Member
0 Kudos

Hi,

You need to set the planning indicator in WBS not Project defination, rest you concept is right.

Reagrds

Former Member
0 Kudos

Hi

Yes I am seting this indicator in wbs element .

but still problem is here.

regards