Does Anybody knows how to change the CN41 report currency? This report usually shows the project costs in controlling area currency. The customer wants to see both, the controlling area currency and another chosen currency.

Thanks

James

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Think currency translation is not covered in case of structure overview reports.

Also you should be using CNS41 instead of CN41.

Regards

Sreenivas