on 05-05-2008 6:17 PM
Hi,
I want to post the GR and to put the material away in several storage type for exemple from 902>922>117-->976.
The TO has been created in background. I confirm the TO through storage unit.
My question: It is possible to confirm the TO more than one time because I have to put the material away 2 or 3 times in different storage type.
Do I need more than one TO for the different confirmations?
Thanks
Dede
Hello Dede,
Avoid multiple posting in different forums. I replied in MM forum for your query.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thats right but it was a mistake because this step belong to WM and not MM
I would like to move the material in the same location but different types.
You said I can move the material from type to type with one TO.
How can I customise the system because when you confirm the TO the first time you can't normaly confirm it for the second time.
thanks
Dede
Hi
You can either only move part of the stock with one TO for each part or when the stock is moved then create another TO to move it again and so on. Once a TO is confirmed that is it.
I think that you have had the answer to your question. I am trying to get people to keep the forum tidy. If you have what you require could you award you points if you want to and mark your question as answered.
This helps everybody as there are at the moment 48 pages of open questions and if people do not close them the forum will grow and then people like me will not go through all of the pages as it takes too long and some people will not get answers to their questions.
Thank you
Frenchy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.