Hi,
Is it possible to post a GR/invoice on an PO item with Internal Order as cost assignment that has TECO status?
The IO was in released status when the PO was created.
Regards,
Ramesh.
Hi
You can't post an GR/IR for a IO having TECO (technically completed) status.
Put back to REL status and post GR/IR.