Hi All...

We are using QM in REM scenario.

There is a inprocess inspection and final inspection..

So what are all the configrtn settings & master datas are to be maintained for this scenario..? ( No costiong relevancy required)

What are the setting required in Mtl Master(FG)..?

How to maintain Rate Routing with QM..? (in-process inpctn & final Insptn) ..?

Please guide me in detail..

with egards,

LN

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member698542
Active Contributor
0 Kudos

Hi LN,

Maintain Inspection Type 13 for Inprocess Inspection REM.

And Maintain Inspection type 04 for GR from Production.

The inspection lots will be generated once you created the Runshdule and after the final Back flush of the assy.

Maintain inspection Plan (Task list type Q) in tranaction QP01.

For inprocess inspection you maintain the Inspection point in the task list.

Thanks and regards

Murugesan

kaushik_choudhury2
Active Contributor
0 Kudos

Hi LN,

You need to maintain the relevent inspection type as active in material master & you have to define the setting for each inspection type as per the requirement viz. Insp with material spec. , Insp with Tasklist etc.

You need to maintain the Tasklist with relevent usage & status . And / or maintain the Material spec.

Maintain the sample drawing procedure . Apart from that you need to maintain other information in SAP

Do let me know if you need any further information

Regards

Kaushik

former_member698127
Participant
0 Kudos

Hi Kaushik...

thanx fr ur rply...

I hav undrstd the settings u hv mentioned.

My quetion is...

As a PP guy what are all d datas i hav to maintain..?

i mean hw to maintain Rate routing for REM with QM..? i mean in routing whether v have to maintain separate operations for in-process insptn..? ( we alrdy select inspctn type in Mtl mstr as 13 - inprcs insptn for REM & 04 for final GR.....) and der is a control key in routing operation PP04 (with incpection char.)...

so hw it wl affect backflushing activities..??

waiting for reply....

kaushik_choudhury2
Active Contributor
0 Kudos

Hi LN,

As a PP consultant you need to maintain the rate routing . You need to maintain sperate operation in rate routing for the QM opeations for inprocess inspection. Also you need to configure the QM control key as per the requirement if you had not done the same.

Let me know if you have any further query

Reward points if you find this info helpful.

Regards

Kaushik