cancel
Showing results for 
Search instead for 
Did you mean: 

Is there a report for cost variance and schedule variance ?

Former Member
0 Kudos

Dear PS Gurus,

We want a report for following two issues -

Schedule variance - Budgeted cost of actual work done / Budgeted cost of work planned to be done

Cost variance - Actual cost of work done / Budgeted cost of work done

Nisarg

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

You can see Cost and Schedule variance in CNE5 Report.

Venkat

varshal_kachole3
Active Contributor
0 Kudos

Hi,

1. You may use the T.code CJ20n, where in you need to go to Project planning board. Click on the icon "Field Selection"

On the right hand side you will find the various field which might be of use, please select them holding the Control key and transfer to the left hand side. Click continue.

2. The other alternative is T.Code CNE5, there also upon excecuting the report for the particular Project, hit F5 and Please select the various fields which are of interest and transfer them to the left hand side. Click continue.

3. The next alternative number 3, Tcode. GR55, search for the report group with 6P* and select any report which is of interest.

Thanks!

Reward point if found useful. And do revert back if not.

Former Member
0 Kudos

Dear Nisarg,

here are some reports for cost and schedule variance.

S_ALR_87013564

S_ALR_87013557

i think it will be helpful to u.

if find helpful reward some points.

Regards

Lallan

Former Member
0 Kudos

Hi,

with the help of the TCode PS91, you can see all the report related to cost/budget of the project.

eg: S_ALR_87013564, S_ALR_87013557

Try this, and if you need some specific report then tel me the details about the input / out put of the report.

Nandan Roy