Dear PS Gurus,
We want a report for following two issues -
Schedule variance - Budgeted cost of actual work done / Budgeted cost of work planned to be done
Cost variance - Actual cost of work done / Budgeted cost of work done
Nisarg
You can see Cost and Schedule variance in CNE5 Report.
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
1. You may use the T.code CJ20n, where in you need to go to Project planning board. Click on the icon "Field Selection"
On the right hand side you will find the various field which might be of use, please select them holding the Control key and transfer to the left hand side. Click continue.
2. The other alternative is T.Code CNE5, there also upon excecuting the report for the particular Project, hit F5 and Please select the various fields which are of interest and transfer them to the left hand side. Click continue.
3. The next alternative number 3, Tcode. GR55, search for the report group with 6P* and select any report which is of interest.
Thanks!
Reward point if found useful. And do revert back if not.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Nisarg,
here are some reports for cost and schedule variance.
S_ALR_87013564
S_ALR_87013557
i think it will be helpful to u.
if find helpful reward some points.
Regards
Lallan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.