on 05-04-2008 11:55 AM
Hi
I need the system to calculate the actual POC, BCWS and BCWP when I confirm the lower level production orders. The calculated value should roll up to my network activities and WBS elements.
For this I have maintained the following:-
1. Maintain Progress Version
2. In Progress version, POC weighting is cost plan (active project, total values)
and EV Basis is Cost Plan (active project, overall values)
3. Define Statistical Key figure for Percentage of completion.
4. Maintain Value Category
5. Assign SKF to value Category
6. Maintained Measurement method in progress in CJ20n (activities,wbs - plan - cost proportional, actual - work)
7. Mentioned POC weighting.
8. Production order is confirmed.
9. Run CNE1
10. In CNE5 I am not getting BCWS and BCWP.
Kindly advise If I am missing any settings. is to possible to update the progress of the project by just confirming the production orders. (i have not confirmed the activities yet??)
thanks and regards
srikrishna
.
make sure that your cost plan in CJ40 donot have any errors.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Srikrishna
Are you able to make the progress analysis to work?
Suresh
Edited by: psconsultant on Oct 2, 2008 4:01 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
U have to confirm the activity.
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.