Release demand to Auxiliary KF

Former Member
0 Kudos

The DP and SNP planning areas are in Production, we have an extra key figure in DP where we want to send the promotions seperatley to SNP. But we donot have any Extra Key figure in SNP, can we use Auxiliary key figure to receive promoitonal forecasts from DP and assign an Order type FC?

what all things i can possibly do with an auxiliary Key figures??

Please suggest.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Not sure if you can do it with an auxillary KF since these dont show up in MSDP_ADMIN where you will have to do the cateogy assignment etc. Auxillary Kf are usually Time Series key figures not Order Series

you can Copy DP KF to SNP KF in time series - again i think you need to have real KF since it will not show up in MC90

Create a copy of the Standard SNP planning area and add another KF. It wont affect anything as long as you cover the change in ur regular jobs