on 04-30-2008 9:24 PM
Hi all,
I'm trying to use the BAPI BAPI_NETWORK_COMP_ADD to create material components, soon after to create the network and activities.
I am filling the NUMBER with the value of temporary network created by bapi BAPI_BUS2002_CREATE.
When I run the bapi BAPI BAPI_NETWORK_COMP_ADD, I get the message 00 058 saying that this network does not exist in table AUFK.
Someone had this problem and know what is the solution?
Thank's very much,
Hi,
You should fill the component BAPI with the permanent network number and not the temporary number. Permanent number is returned by create BAPi after commit.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For those who are still looking for the solution of this problem - refer to note 672750. As per this note you need to do some initialization. So just put a statement before BAPI_NETWORK_COMP_ADD call:
CALL FUNCTION 'CO_ZF_DATA_RESET_COMPLETE'.
and the problem will be solved.
Try maintaining the valuation category ( in accounting view of the material) and then execute the BAPI
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.