on 04-30-2008 3:20 AM
Hi
I am doing the BPM scenario for collecting the MATMAS IDoc ...hwen i checked the BPM in SXMB_MONI when i press the PE then its showing IN PROCESS status..
What could be reason .. there should be any configuration i have to do in SXMB_ADM or its a just design issue
SV
go to the sxmb_moni_bpe to check the step, which is running and taking a lot of time
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
I set up the endcondition as 1 = 1 ( i think thats one for Infinite loop ) thats causing the problem
In SXMB_MONI the column nect to PE is in a Clock status
SV
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi S V,
--> What is the status code in sxi_cache for your BPM scenario?
--> check, if any thing is there in smq1&smq2
and let us know.
Regards,
Ramesh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello SV,
Click on the PE in the SXI_MONITOR and go to the workflow log of your BPM and check on which step did it finish.
Then go to the technical workflow log and you'll see the error click on it twice.
refere to this:
https://websmp203.sap-ag.de/~sapdownload/011000358700003141152005E/HowTo_Monitor_ccBPM.pdf
Check this document for troubleshooting BPM..
BPM Tips and tricks
https://www.sdn.sap.com/irj/sdn/wiki?path=/display/cpm/bpm%2btips%2band%2btricks
Thanks,
Satya Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Do check whether the 'end' condition that you would have set in the loop is getting satisfied for a particular input IDoc.
Thanks,
Anand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
should be any configuration i have to do in SXMB_ADM?
you don't need to any configuration in SXMB_ADM.
its a just design issue?
This may be a design issue.
Are you using correlation in design of integration process.?
If yes then may be BPM is waiting for he successful execution of correlation.
As mentioned in above replies from sxmb_moni by clicking on PE you can see workflow of your BPM and come to know which step of your BPM is in waiting step.Check properties of that step in your integration process.
If you are still facing problem then you can let us know.
Regards
Sami
Reward points if helpful.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
10 | |
9 | |
9 | |
9 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.