on 11-23-2005 1:59 PM
HI,
we are using a BPM (a big one) with a Multimapping zMATMAS03(Source) & RFC(Source) to MATMAS05(Target).
The source(zMATMAS03) IDoc has a extension(German Erweiterung) with new Segment ZZxxx and new Fields ZZyyy.
What happen if the allready importet and mapped zmatmas03 Idoc will be changed in the source system ?
Example. We added 2 new Fields in the old zzxxx segment.
Did i have to map everything new if i import the new idoc ? or did the new field are added to the old idoc and the mapping is working again ?
Regards,
Gordon
Hi,
1. you have to reimport the idoc from IR
2. you should delete the old idoc definition in TCODE - IDX2
3. you have to change your mappings so that they will use the new IDOC
Regards,
michal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
10 | |
10 | |
9 | |
7 | |
6 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.